While the previous draft solar PPA does not require the Feed-in-Tariff (FiT) conversion between USD and VND be according to the exchange rate at the time of payment, this newly issued solar PPA repeats the language in Decision No. 11/2017/QD-TTg (Decision 11) that the FiT will be adjusted according to the fluctuation in the VND/USD exchange rate. This is consistent with what is stipulated in Decision 11.
In addition, I note that while the FiT for power output from on-grid projects is adjusted according to the fluctuation in the VND/USD exchange rate, meaning at any time during the year, it is not the same for rooftop projects. Instead, the mentioned FiT for excessive power output generated from rooftop projects remains the same throughout the first year of operation, and the new FiT for the next year will be adjusted based on the announced VND/ USD exchange rate of the last working day of the previous year.
2. Are there any concerns of investors that the solar PPA has not solved?
The rights of the investors are not fully protected in the following cases:
– when EVN is in the process of installing equipment, or making repairs, replacement, inspection or examination of the grid connection of the seller’s power plant;
– when the transmission grid or the distribution grid connected to EVN’s grid has a problem or grid equipment directly connected to EVN’s transmission grid or the distribution grid has a problem; and
– when EVN’s grid needs support to recover after the incident in accordance with the provisions of operation of the national power system and the standards, technical regulations of the electric industry.
– allocation of feeding points into the grid
It is quite risky for the producer if the output is ready to be fed to the grid but the connection is not available to do so. Absent a clear indication of whether the Solar PPA is a ‘take or pay” agreement, investors will find it difficult to secure and ensure the profits and revenue of their projects.
This PPA is not bankable due to reasons specified in 2).
There is an increasing interest of foreign investors in the sector, proven by the fact that there are many solar projects with total capacity of 10,000 MW registered with the MOIT. However, not many of them have submitted the pre-feasibility study to the MOIT for consideration. There are many reasons behind this, but the most important ones are the lack of Government guarantee of EVN’s payment obligation in the PPA and currency hedging. Thus, the Government should consider a mechanism where EVN has to fulfil its payment obligation and the investors are ensured that they will be able to remit their profits abroad in foreign currency.
Incoterms 2020 chuyên biệt cho đường hàng không 1. 🌐 Giới Thiệu: Tại Sao Incoterms…
1. 🌐 Xác Định Vai Trò Của Forwarder Trong hàng không, vai trò của Forwarder…
Các chứng chỉ nghề nghiệp quốc tế trong ngành Air Cargo 1. 🌐 Tại Sao…
Quy định về Kiểm soát xuất khẩu (Export Control) và Cấm vận 1. 🌐 Giới…
Thủ tục tạm nhập tái xuất (ATA Carnet) bằng đường hàng không 1. 🌐 Giới…
Hệ thống băng chuyền và Tự động hóa kho hàng không (AS/RS) 1. 🌐 Giới…